Early cost estimate for a route scheme

Price a route scheme at your own rates.

Attach the route and the points planned along it, and give your rates. You get the lengths and counts priced, as a table with a map.

Free to start. No card.

Or ask for
Moston Busy Beeway: Route and Active Travel Scheme Features
A street map of north-east Manchester with a protected cycle route drawn in teal from Greengate south-west through Moston and Newton Heath to Miles Platting, with active bus stops in blue, proposed crossings in green and junction improvements in amber along it.
On the route
Active bus stops31
Proposed crossings6
Junction improvements2
The route5.924 km

Each item’s pop-up gives its distance along the route and from the line.

A Busy Beeway in north-east Manchester, with every counted item on it coloured by type.

For whoever needs the first figure

Active travel teams.Highways engineers.Scheme sponsors.

Long before the design, someone needs a figure for the business case, and has to show where it came from.

An early estimate is quantities times rates: kilometres of track, and so many crossings, junctions and bus stop bypasses, each at your rate, plus a margin. Measuring and counting them is the quantity take-off.

Here you attach the route and the lists, and say what counts. Every line of the estimate goes back to points on the map.

One real scheme

One Busy Beeway in Manchester, priced line by line

A confirmed Bee Network Busy Beeway, a protected cycle track along a main road, from Greengate on the Middleton boundary to Queens Road in Miles Platting. The route, crossing points and Mayor's Challenge Fund points came from Transport for Greater Manchester's open data, the bus stops from the Department for Transport's NaPTAN list.

Works
£10.08M£10,076,400 for track, crossings, junctions and bus stop bypasses, at your rates
Margin
£3.02M£3,022,920, the 30% for design, contingency and optimism bias
The estimate
£13.10M£13,099,320 for the scheme, with every line shown
The works, line by lineCost
Protected cycle track£6,516,400
Bus stop bypasses£1,860,000
Proposed crossings£900,000
Junction improvements£800,000

It prices only what you ask it to count.

Crossing points marked proposed, not the existing ones. Bus stops in use, not the inactive ones. Mayor's Challenge Fund points by their own code, so a CYCLOPS junction and a junction improvement each take their own rate.

Transport for Greater Manchester, Bee Network open data: the route, crossing points and confirmed Mayor's Challenge Fund points. Department for Transport, NaPTAN bus stops for Greater Manchester. Both Open Government Licence. Unit rates and the 30% as set in the request. Run on 15 November 2026.

Quote a range, not one figure

Keep the quantities, change the rates, and set the two side by side.

Crossings and junctions kept their rates, so only the track and the bypasses moved.

Same quantities, but track at £1.6 million per km and bypasses at £90,000 each. Set it beside the first as low and high.

It set the high estimate beside the first, line by line, with the subtotal, the 30% and the total in both columns, and gave the range to quote: £13.10M to £18.16M.

Cycle track
6.52
9.48
Bus stop bypasses
1.86
2.79
The estimate
13.1
18.16
Low rates, £ millionHigh rates, £ million

How it goes

  1. Attach the route and the lists and state your rates.

  2. Mapstack maps what it counted, coloured by type.

  3. You get every item in order, with its distance from the start: its chainage.

Common questions

What happens to our scheme data?

  • It stays in your workspace. Only people with a seat in your workspace can see it. Nothing leaves unless you publish it yourself.

  • It is not used to train AI. Your data and your conversations are not used to train AI models.

  • It is still yours. You keep ownership of what you bring in. Delete it and it is removed.

The full answer is in the documentation: Your data, privacy and security.

What does it cost?

  • Free to start. One seat, for you, with a starter amount of work each month. No card.

  • This job is on the free seat. Maps, datasets, analysis, your own files and public sharing are all included.

  • Pay per person for more. A paid seat brings more work each month, and seats for your team.

The prices are on the pricing page.

What goes into the estimate?

  • Your rates and your margin. Per kilometre and per item, with the percentage you add on top.

  • Your distance. Anything within the distance you name of the line counts as on the route.

  • Your rules for what counts. By status, by code, active or not, from the columns in your files.

Price yours.

Free to start. No card.